Question :

Elements of a WBS for a project to build a bunk bed are given. Using the information supplied here, create a WBS and carry out a bottom-up cost estimate.

Answer :

Following are elements of a WBS for a project to build a bunk bed. Using the information supplied here, create a WBS and carry out a bottom-up cost estimate.

  Cost($) Rate ($/hr)  Time (hrs)
Research : Jimmy' time      1 2 
 Dad's time   25  2 
Materials:  Lumber  200    
 Hardware  45    
 Power equipment rental  65    
  Jimmy's time to acquire materials     1  3
 Dad's Time to acquire materials    15 3 
 Construction :  Jimmy's time    1 8 
 Dad's time    20 8 
Inspection:  Mom's time    10 0.5 

Gantt chart:

managing-projects-in-organization
 

Cost Estimation:

1. Research $52.00 
2. Material $388.00 
3. Construction  $208.00 
4. Inspection  $ 5.00
  Total: $653.00

 

Download Full Sample Here
HIRE EXPERT
Email ID *
Subject
Pages
Deadline


Thank You!

We will get back to you as soon as possible.


Your friends could use our help too! Tell them about us also!